GUIDE
A delivery is not a handover. Before a mobile slaughter trailer leaves a China manufacturer, it can be cleaned, chilled, measured and recorded against a checklist you wrote yourself.

Acceptance testing proves the unit matches the specification you wrote, under the conditions of the test. It does not prove the unit is approved in your country. Write three documents before the deposit: the technical specification, the drawing sheet and the factory acceptance checklist, stating which readings must be produced and which values are acceptable.
Most hygiene problems are design faults, not operator faults: a seam that cannot be wiped, a floor that ponds, a drain in the middle of the kill area. All are cheaper to fix in the factory than at your gate.
| Check | How | Fails when |
|---|---|---|
| Weld and joint finish | Run a finger along every seam | Rough seam, exposed fastener |
| Kill floor drainage | Pour water, watch the gully | Water pools away from drain |
| Food-contact material | Ask the grade of chamber and rail | Grade not stated |
| Hanging rail and trolley | Load to the specified head count | Rail sags, trolley jams |
| Carcass entry and exit | Compare door width with your carcass | Carcass must be twisted |
Two checks are worth doing personally. Walk the kill path from animal entry to chiller and back to the loading door: a carcass and a worker should both move through it without reversing. Then run water across the kill floor and watch where it goes.
Ask for the cleaning routine, not only for cleanability. Four items in writing: water consumed by a full clean, how long the clean takes with your crew, whether hot water is available for wash-down and at what temperature, and where wash water goes.
Chilling performance is checked least and regretted most. A compressor that runs and a chiller that pulls down are not the same claim. The test that separates them is the pull-down record: product temperatures taken at intervals, with the doors handled realistically.
| Reading | Taken when | Why |
|---|---|---|
| Core temperature at the cut surface | At dressing, before the chiller | Sets the starting point |
| Core temperature at 4 h and 8 h | Fixed intervals during the run | Shows the rate of cooling |
| Air temperature at rail level | Logged with carcass readings | Air-only readings hide poor airflow |
| Door openings and duration | Every time it is opened | A test opened hourly is not sealed |
| Ambient temperature | Logged with refrigeration running | Same machine, different yard |
Three rules make that record meaningful: take readings from the deepest part of the carcass, log door openings and their duration, and state the ambient temperature. If a supplier will not put these readings in the acceptance report, cooling capacity has been asserted rather than demonstrated.
Send the checklist before production starts, not at the end. List the readings the factory must produce: rail load at the specified head count, the chiller pull-down record, a generator load test at the specified output, water and waste tank volume measured by actual fill, and a functional test of every valve, pump, door and safety interlock in turn. Decide who witnesses: a video call with a phone inside the chiller is enough for a standard configuration, while a customised first order is usually worth a third-party inspector, because the same report becomes your import file.
Do not guess the regulations and do not accept a supplier's summary. Ask the competent authority three questions in writing before you order: whether a mobile slaughter unit must be registered or inspected as a food premises in your region and who inspects it; what temperature, record-keeping and transport duties apply to the holding period and to moving product off the site; and which documents must accompany the unit at import.
This order of operations keeps a sourcing project from stalling, whatever the destination.
| Stage | Confirm | Keep as evidence |
|---|---|---|
| Vet the factory | The workshop builds units like yours | Dated walk-through, licence |
| Freeze the specification | Drawing, rail, chiller, tanks, power | Signed spec, one revision |
| Inspect before shipment | Acceptance test run | Signed report, photos, readings |
| Payment terms | Deposit on drawing, balance on inspection | Contract wording, not verbal |
| Shipping terms | Who books, who loads | Weights, dimensions, packing list |
| After delivery | Wear parts, diagrams, a named contact | Spares kit, manuals, response time |
Two answers matter more than the rest. The export question is not whether the supplier exports, but under which document and with which declaration of conformity the unit enters your country: some markets treat a mobile slaughter unit as a machine, others as a food premises. The electrical package must be fixed in the order: voltage, phase, frequency and plug type, because a three-phase 380 V unit will not run from a single-phase supply, and a 60 Hz motor on a 50 Hz grid runs slow and hot.
For loading and lead time, a trailer of 6-8 m does not fit inside a standard 40 ft container and normally travels on a flat rack or by RoRo, while a container-based unit ships as an ordinary container. Ask for build weeks and sailing weeks separately. On support, request the wear-parts list with part numbers, wiring diagrams for the refrigeration and electrical panels, a first-year spares kit, and a named technical contact with a response time in the contract.
HUAYI EQUIPMENT builds mobile slaughter trailers and container slaughter units in China, shipped with a loading plan, an electrical specification, an acceptance checklist and a spares list for the destination country. Send your species, peak head count, carcass weight, available power, destination country and port, and we will return a configuration with rail length, tank volumes and the test list.